Have
Contracts been Voided because of Corona?
A
Summary of Pakistani Law on “Force Majueure”
By Umer
Gilani
and
Omer Imran Malik,
Law and
Policy Chambers
Since mid-March, Pakistan has
been in the grip of an emergency situation because of COVID-19. On 17th March, 2020, the
Government of Sindh issued orders for a partial lockdown. On 23rd
March, 2020, the Prime Minister of Pakistan, in a televised address, promised
to follow a different policy. However, the same day, the PTI-led Government of
Punjab also followed the example of Sindh. That day, the Home Secretary of Punjab
issued Notification No. SO(IS-II)1-1/2004 under Section 144 of Code of Criminal
Procedure, 1898. Although Punjab did not call it a “lockdown”, it was, for all
effects and purposes, the same thing. The next day, the Deputy Commission of
Islamabad Capital Territory also passed similar notifications. As a result, it became illegal to open almost
all kind of workplaces other than pharmacies and groceries.
As a result of the lockdown,
most enterprises in Pakistan (not just exporters) have not been able to
generate any substantial business in the last three weeks. In the context of
this emergency situation, the legal questions which naturally arise are:
Are enterprises
still bound to pay rent for the post-Corona period?
Are enterprises
still bound to pay interest on loans to financial institutions?
Are enterprises
still bound to complete those contracts which they had partially performed pre-Corona?
The short and sweet answer to these
legal questions is: It DEPENDS. That may not be the re-assuring, one-size-fits-all answer you were looking for. But that is, in fact, the answer.
The primary legal text which
you should read and understand in this situation is the second part of Section
56 of the Contract Act, 1872. It’s simple
English and you don’t have to be lawyer to read this:
S. 56. …
Contract to do act afterwards becoming impossible or unlawful. A
contract to do an act which, after the contract is made, becomes impossible,
or, by reason of some event which the promissor could not prevent, unlawful,
becomes void when the act becomes impossible or unlawful.
From a plain reading of this text,
it is clear that you can walk out of your contract if you can establish either of
these two situations: it has become “impossible” to perform; or it has become “unlawful”
to perform.
As you analyze your situation in
the light of Section 56 of the Contract Act, please bear in mind that contract
law is an area of law where facts are critical. Even in the backdrop of the
same emergency, the facts of each case can vary widely. Therefore, it is not
possible to give a one-size-fits-all answer to this question.
In addition, you must also carefully
read the “force majeure” clause of your contract, if at all there is such a
clause in your contract. If you have a clause like that, read it closely, ten times. The language of every person's contract is different; and the sum total of my review of case law is that language of force majeure clause matters.
Please note that in Pakistan “force majeure” clauses
rest on purely contractual footing. Our situation is, in this regard, radically
different from that is civil law countries such as Europe, China, Japan and Arab world
etc. where the doctrine of force majeure – a doctrine whose origins can
be traced back to Roman law and the Shari’ah – is codified in statutes. If you search
for the word force majeure in our Contract Act, 1872, I am afraid you won’t find
it. Section 56, which is based upon the English law doctrine of ‘frustration’, is
the closest you will get.
To sum up, roughly speaking,
whether you can walk away from your contractual responsibility on account of
the present situation depends, essentially, upon two things:
(i)
Whether, in the present situation, performing your part of the contract has
actually become “impossible” and not just “inconvenient”? and
(ii)
whether the language of the “fore majeure” clause in your contract, if at all there
is such a clause in there, adequately covers the situation at present.
In my next post, I will be providing
a more detailed exposition of how Pakistani courts have, over the years, interpreted
the term “impossibility” used in Section 56 of the Contract Act. I will also be
providing you examples of situations where Pakistani courts have allowed party to
invoke “force majeure” clauses. Because we are a precedent-based legal system,
analysis of case law is essential to come to any conclusion about whether you
can skip this month’s rent payments and interest payments.
If you are a lawyer yourself, the
three most important cases on this subject which I recommend you to read are: Atlas
Cables case 2016 CLC 1677 (Islamabad), Quinn Corporation v. Raw Cotton
Corporation 2004 CLD 1040 and Kadir Bakhsh v. Province of Sindh 1988 CLC 171
Until the next post…